BUTLER TWP — The Butler School Board has approved summer roofing projects at Butler High School and Summit and Oakland Township elementary schools.
The board approved an $879,000 contract at its meeting May 20 with Pennsylvania Roofing Systems of Bakerstown.
The contract is nearly $80,000 less than was budgeted for the project. Funds from a 2012 bond refinancing will be used to repair the roofs.
Other repair projects planned for the summer include rebuilding the intermediate and high school running tracks for $617,500, and paving projects that total $178,000.
At that same meeting, the board approved refinancing the $2.6 million Series 2003 A bonds to net about $51,000 in savings.
The board unanimously rejected an opportunity to borrow an extra $5 million for other capital projects as part of the deal.
Without the additional borrowing, the district’s indebtedness will stay at $115 million. The district’s debt payments run from $4 million to $5 million annually.
The additional funding would have paid for capital projects, including roof replacements at district elementary schools. That plan lost steam after the board agreed to hire a facilities planner to consider consolidating the 11 neighborhood schools.
Roof replacements might be more expensive than the value of an elementary school in the real estate market, said Jim Keffalas, a Realtor.
Keffalas recently appraised the empty Bruin Elementary School building at $236,500. It has been on the market since June 2012.