KARNS CITY — Karns City Area School District’s board took another step toward $40 million-plus in upgrades to its junior/senior high school Monday night, Nov. 16, by approving plans from the “design development phase” of renovation efforts.
Plans include renderings prepared for the high school project by Hayes Design Group and Eckles Construction Services, along with estimated budgets.
The district will now proceed with the “construction documents design phase,” a point where documents — such as specifications, permitting applications and in-depth blueprints — will be drawn up.
According to John Pappas, project manager and president of Eckles Construction Services, the project has received two cost estimates from two separate groups.
One of those estimates puts the potential renovation cost at $39.486 million, with site improvements and a gym addition bringing that number to just over $44 million.
A second estimate projects the renovation cost at around $36.5 million and a total project cost at around $42 million.
“Since we’ve all last spoken, there’s been some small updates made to the site plan. We’ve also taken another pass at the interior design renderings, taking on more of a school-pride theme as opposed to the initial proposed options. That was just based on some feedback the administration collected,” said Matt Dawson, of Hayes Design Group.
The project will include facility updates, such as new and improved classrooms and learning spaces, improved athletic facilities and significant heating and cooling improvements.
The project is informed by a series of surveys taken by teachers, faculty, department chairs, athletics employees and other key stakeholders since February.
A presentation by Hayes on Monday night showed an updated site plan that includes an expanded south parking lot with a relocated driveway entrance, a sidewalk added around the east side of the building to connect the north and south lot, improvements to ADA compliance, pedestrian and vehicular access to the stadium and an addition of nearly 90 new parking spots.
Located along Kittanning Pike just before it turns into Main Street, the high school holds students in grades 7-12. Mostly built in 1981, with some physical portions dating back to the early 1960s, the high school currently has just over 600 students.