Callery bridge replacement project to begin April 1

The state Department of Transportation is expected to begin the $4.06 million Callery Group Bridge replacement project in Callery Township on April 1.

The project, which runs through the end of October, will include the construction of a new bridge and stream restoration on Breakneck Creek.

During construction, there will be a full road closure on Kline Avenue. Motorists should detour by going from Kline Avenue to Mars-Evans City Road and continuing north to Evans City, where they turn left on East Main Street, turn left onto Pioneer Road/Franklin Road, turn left onto Callery Road, then turn left onto Kline Avenue.

Chivers Construction Company will be completing this project.