VA builder seeks 8-year tax diversion

Money slated for drainage system

BUTLER TWP — Westar Development is seeking to divert about $3.2 million in property taxes for about the first eight years of the new VA Butler Healthcare center being built at Deshon Woods.

Westar of Aurora, Ohio, has financing in place for the $75 million project, as well as a 20-year lease from the federal Department of Veterans Affairs, said Doug Linn, an attorney representing Westar at Monday’s meeting of the Butler School District finance committee.

Westar is seeking to have $3.2 million in taxes diverted from the school district, Butler County and Butler Township to pay for a $2.5 million underground drainage system, including a stormwater retention tank, at the 16-acre Deshon Woods site on Route 68.

Market conditions have changed since project financing began and wetlands at the site “vastly increased” the development company’s costs, said Sam Calabrese, president of Westar and principal-in-charge of the project.

Under Westar’s plan, a Tax Incremental Financing district, or TIF, would be established to allow for real estate tax revenues to repay $3.2 million in TIF bonds. The funds would be earmarked for infrastructure improvements, Linn said.

Linn said he hopes the three government bodies will make a decision on the TIF in April. All three must approve the TIF.

“We need to get an idea if this is something they would entertain,” Linn said.

After the TIF bonds are paid, the government bodies would split about $440,000 in annual taxes from the facility for the following 12 years, with about two-thirds going to the school district. That amount does not include any tax increases that might occur, Calabrese said.

VA Butler Healthcare is tax exempt. Under Westar’s plan, the taxing bodies could collect real estate taxes for up to 52 years, since the new project is expected to have a 60-year project life.

It would support 375 jobs, 50 more than the VA facility has now, Calabrese said.

Deshon Woods is adjacent to the existing VA Medical Center. Westar bought the property from Butler Township for $2.38 million. It also bought six acres from Butler Memorial Park cemetery for an undisclosed amount.

On Monday, Westar made an informal presentation on the TIF proposal to the Butler County Commissioners too, Linn said. A formal presentation will be made at a later commissioners meeting when the TIF resolution is presented, he said.

The company’s principals also will make a presentation to the Butler Township Commissioners at their meeting at 6:30 p.m. Monday.

According to brochures distributed at the school district meeting, the new facility must be ready by May 2014 or the “VA will step in and take over the project, making it tax exempt.” Calabrese said the VA would buy the property from Westar.

The VA’s incentive for the project is that Westar is expected to run the facility for about $7.6 million annually, about $2.4 million less than the VA spends annually now, Calabrese said.

The new facility will be both smaller and more efficient, he said. The new building is expected to be 225,000 square feet compared to the 277,000 square feet of the current facility.

It would include more clinical space than the existing building, to serve veterans from 13 counties, Calabrese said.

Linn told the school board, “What we’re asking you to do is to create state of the art facilities for our veterans.”