BASA counts sewage permit availability
Butler Area Sewer Authority is concerned it may run short of sewage permits for a number of proposed developments.
John Schon, BASA’s operations manager, told the authority board Wednesday that T&R Properties of Dublin, Ohio, has told BASA it plans to develop an acre and a half at Henricks Road and Glenwood Way in the Meadow Brook apartments plan in Center Township.
T&R plans to build two 16-unit apartment buildings and two six-unit condominium complexes on the site.
That development would need 44 EDUs or equivalent dwelling units, and Schon and the board said they are concerned that if T&R were to get the 44 EDUs and sit on them for a length of time, it could be a detriment to other projects in the BASA area.
Schon said BASA has 195 EDUs available, plus an additional 45 EDUs that stem from a permitting process the state Department of Environmental Protection allotted BASA in 2006.
At that time, the DEP put a hold on all sewage permits for BASA, linking them with the authority’s work on correcting a stormwater sewage overflow problem.
Since 2006, BASA has requested 200 sewage permits per year on an annual calendar of April 1 to March 31.
Even though the authority has more than 200 permits, Schon said he is concerned that with the annual request period coming up soon and the authority’s stormwater management project nearing completion, that the DEP may change the way it has been issuing permits to BASA.
He said the development of a new Sheetz store on Route 8 at Vogel Road will require 25 EDUs; the construction of a 25-unit apartment building on Alameda Road behind the Wendy’s restaurant will need 25 EDUs; and the new VA Butler Healthcare medical center on Route 68 will need 80 EDUs.
When asked by board members how fast Schon thinks T&R will be moving to construction, he said the company has not yet presented its plans for Center Township approval.
Schon speculated that T&R Properties is looking for funding for the apartment construction and needs documentation from BASA that will show that it will be able to get the sewage permits when it needs them.
The authority board voted to approve the 44 EDUs for the T&R project, if they are bought by March 31. After that date, T&R will have to make its request again.
Mike Hnath, BASA solicitor, said by that time BASA should have a better idea from the DEP on how many permits BASA will be getting and under what conditions.