School district may purchase new computers
BUTLER TWP — The Butler School District may replace 121 elementary school library and laboratory computers in January at a cost of about $50,000, or $399 each, said Jerry Slamecka, assistant superintendent for technology.
Slamecka gave the school board a draft, three-year plan at their meeting Monday night to replace 904 computers in all the district’s elementary and secondary schools’ computer labs and libraries. It does not include 350 computers used by teachers.
“Jerry is so conscientious, he doesn’t want to leave anything undone,” said Mike Strutt, superintendent. Slamecka is retiring after 43 years with the district. His last day at work is Dec. 21 and his duties will be distributed among other employees, Strutt said.
Under the computer plan, in January the district would replace 121 computer processors, called CPUs, that are at least 10 years old and are located in libraries and computer laboratories at Northwest, Emily Brittain, Center Township and McQuistion elementary schools. The district would keep the computer monitors it has, Slamecka said.
If the board approves the plan, the CPUs would be purchased from Open Arc, a Wexford-based firm that also supplied the district’s $710,366 telecommunications upgrade, Slamecka said.
The telecommunications upgrade included new data transmission switches, some wireless network upgrades, wireless network installations in all three secondary school auditoriums and Internet-based telephones for the district.
“This (computer replacement) plan does not yet include software licensing for Windows 8 and MS Office 2013,” Slamecka wrote in a memo to the board. “We are still trying to establish costs for these licenses through Pennsylvania state licensing agreements that are supposed to be available to school districts.”
Existing computers use the Windows XP operating system, which is losing technical support, he said.
In addition, the plan suggests replacing CPUs at the junior and senior high schools in March, and at three intermediate high school labs in September.
In Jan. 2014, CPUs would be replaced at labs and libraries at Broad Street, Center Avenue, Clearfield, Meridian and Summit elementary schools under the plan.
In Sept. 2014, new computers would be installed in additional labs at the intermediate high school. Remaining stations at the senior high school, junior high school and Northwest Elementary School would be replaced in Jan. 2015.
Although the district could use capital funds to purchase all the computers at once, it spreads out technology purchases so that all hardware and software are not obsolete at the same time, Strutt said.
In addition, the district’s capital funds are needed for roof repairs and textbook purchases, Strutt said.