Board talks about security
SLIPPERY ROCK TWP — The Slippery Rock School Board on Monday further discussed security options for its five buildings.
Two directors differed over the direction of the district’s security measures.
Architects from HHSDR Architects of Pittsburgh and Sharon earlier in March presented two plans for the high school.
The first option features a main entrance with a security vestibule, five locked access doors and a new fitness center.
The second option features a main entrance with a security vestibule, six locked access doors and a new office and main entrance featuring a security vestibule.
The district’s three elementary schools would have a security vestibule at the main entrance that would lead into the office, to be used by visitors, and four access doors with card readers and electronic latches for use by teachers.
The middle school would have a security vestibule at the main entrance and two access doors with card readers and electronic latches. The district’s administration office, located at the middle school, would get a security vestibule at its entrance.
The high school’s first option would cost $2 million and the second option would cost $1.67 million.
The elementary school projects are expected to cost $261,000 at Har-Mer, $340,000 at Moraine and $376,000 at Slippery Rock. The work at the middle school is expected to cost $207,000.
School board member Kirby Lotz said that he is not sure if the plans are the right thing to do. He said the money that would be spent on the projects could be spent on putting armed guards in the district’s buildings.
“I don’t think it’s a bad start, but it’s not enough,” Lotz said.
He said he would rather have guards in place first before putting new doors in.
School board member Mark Taylor said he felt that the plans are a good start.
“We need to do something,” Taylor said.
The middle and elementary school projects could be done by August, and the high school project likely would be finished in August 2014.
Architects said that the middle and elementary school projects should be voted on as soon as possible, but the board can wait a bit to vote on the high school project.
Paul Cessar, business manager, said that the district needs a contract written up to be able to vote on the projects.
Board President Michael Scheer said the board should have a contract put together so the board can further discuss the projects and vote on them.