Renovation project delayed

The biggest project for Slippery Rock University this summer is the $24.5 million renovation of Millier Auditorium. The project, scheduled to begin in the spring, is behind schedule because of complications.
SRU set for other work

SLIPPERY ROCK — With the spring semester complete, Slippery Rock University is working on a busy summer construction season.

The biggest project is the $24.5 million renovation of Miller Auditorium.

Herb Carlson, vice president for construction design and management, said the initial plan was to begin construction in spring.

However, the project has gotten a bit behind schedule due to complications.

“I would say (the designers) lost about two months,” Carlson said.

The designers took the design to the state Department of Labor and Industry, which rejected the design, saying that the building's lobby required a smoke evacuation system.

The designers said that it did not, but the department said that it still did.

The designers took the matter to the state Industrial Board, which agreed with Labor and Industry. The designers currently are appealing to the Labor and Industry chairman, while designing a smoke evacuation system in case they lose the appeal.

Once the chairman makes a decision, the design will be approved by the department. Then, it will go the state budget office and then it will go to bid.

If the process goes according to plan, bidding for the project could begin in July.

Carlson said the hope is to start construction in early fall.

“That's kind of the earliest it can start,” Carlson said.

He said that construction will take about 400 days.

The building is being designed as a joint venture of R3A Architects of Pittsburgh and Westlake, Reed and Leskosky of Cleveland, Ohio.

The building, which is 22,803 square feet, currently has an 800-seat auditorium, a lobby and dressing rooms.

The project will add a 300-seat dance performance space, a “black box” theater with 300 seats, additional rehearsal space, classrooms, offices and an expanded lobby.

When completed, the building will be 58,753 square feet.Several other projects will be going on at SRU this summer.Kraus Hall, a former residence hall that has been closed for several years, finally will be demolished this summer and a parking lot will be constructed on its former site.It initially was supposed to be demolished shortly after it closed, but the state would not release any money for the project until now.Carlson said that demolition will cost about $400,000 and the parking lot will cost $400,000.“So, that's a lot of money,” Carlson said.He said that the demolition hopefully will take place at the end of the summer.The swimming pool area of the Morrow Field House will be renovated at a cost of about $600,000. Carlson said the walls of the pool have started to leak and will be replaced. Additionally, the pool's drain will be replaced.The pool will be closed all summer for the project.SRU will be replacing some older steam lines on campus at a cost of $800,000 and the student government association has paid for a dek hockey rink, which will cost $165,000.

Kraus Hall, a former residence hall that has been closed for many years, will be demolished this summer. Slippery Rock University will construct a parking lot on its former site. The demolition will cost about $400,000, the same amount it will take to build the parking lot.