The Cranberry Township supervisors took the following official action at Thursday’s meeting:

Granted a lot line revision to create six units on one lot on Moyer Hill Drive in the Eagle Hill development

Adopted a resolution granting a lot line revision conveying 1.59 acres from Green Field Estates’ open space to Graham Park

Extended the completion date from Nov. 30 to Dec. 31 for Independent Mechanical’s Rotary Amphitheater expansion work

Approved a change order amounting to $10,760.54 to Hranec Sheet Metal Inc. for mechanical construction on the fire station expansion renovation.

Approved the following partial contract payments:

$1,392,214.41 to Allegheny Excavating Inc. for construction on the MSA Thruway

$21,859.49 to Freedom Enterprises & Associates for general construction on the Rotary Amphitheater expansion

$165,296.20 to Stefanik’s Next Generation Contracting Co. for work on the Goehring Road water line project

$23,230.01 to Hranec Sheet Metal Inc. for mechanical construction on the fire station expansion renovation.

Partially released the following bonds:

$55,143.90 to Eckles Construction Services Inc. for Phase 2G of Village of Cranberry Woods

$142,715 to Glen Eden Road Partners LLC for Phase 1 of Links of Cranberry, Davis PRD

Adopted Little Pine Drive in BelleVue Park Phase 2 into the township road system

Approved a renewal of two agreements with Delta Development Group to pursue and administer MSA Thruway, BUILD and INFRA grants

Passed a resolution establishing the maximum allowable headworks loadings for the Brush Creek Water Pollution Control Facility.