Cranberry Township supervisors took the following actions at the Thursday virtual meeting:
Extended the at-face value property tax payment deadline to Nov. 30
Approved a resolution raising rates for grading permits
Granted preliminary and final land development and conditional use approval for:
A 20,400-square-foot addition to an existing office/water house at 230 Thorn Hill Road
Phase 2 of a two-building construction on Thorn Hill Road
An 18,500-square-foot addition to an existing light manufacturing plant at 1000 Cranberry Woods Drive
Approved the following change orders:
A $13,000 addition for electrical construction to Westmoreland Electric Services for the Brush Creek Water Pollution Control Facility expansion project
A $2,881.10 addition to Traffic Control & Engineering for the traffic signal replacement on Route 19 and St. Francis Way
An $18,574 reduction to Ferri Contracting for repair allowance not used on the water tanks valve project
Granted the following contract payments:
$25,974.05 to D&G Mechanical for HVAC construction on the Brush Creek water plant project
$52,248.77 to Shipley Bros. Plumbing for plumbing construction on the Brush Creek water plant project
$47,167.27 to Westmoreland Electric Services for electrical construction on the Brush Creek water plant project
$45,143.66 to Traffic Control & Engineering for work on the traffic signal replacement at Route 19 and St. Francis Way
$69.547.48 to Ferri Contracting for work on the water tanks valve project
Awarded the following contracts:
$84,663.60 to Peter J. Caruso and Sons for micro-surfacing
$99,175.05 to CASMAC Line Striping for line painting and traffic markings
$42,530 to Wm. T. Spaeder Co. for blow intake acoustic silencers at the Brush Creek plant
$263,800 to Joseph J. Brunner for disposal of biosolids, grit and screening at the Brush Creek plant.