Bridge to reopen by end of May
WINFIELD TWP — The township will bridge the gap on Marwood Road. Denny’s Mills Bridge is set to reopen by the end of May.
Kevin Gray, the Butler County planning/bridge manager, said construction of the new 50-foot structure, which replaces a deteriorated 39-foot bridge, was delayed due to personnel changes in the former West Penn Power.
“That was our biggest hang-up,” he said. “(It’s) one of those things happening you don’t anticipate.”
Gray said the company, which was absorbed by First Energy, had to cut electricity to four homes while the bridge’s concrete beams were set Wednesday.
Power was shut off to those homes for three hours while the work was done.
The project originally was scheduled to be done at the end of 2012.
The township paid the county $200,000 to replace the old bridge due to rotting steel beams and loose stone.
To fund the work, Winfield took out a 10-year loan from PNC with a 3 percent interest rate.
Township Supervisor Mike Robb, board chairman, said the long winter also contributed to the delay.
Robb said now that the beams are set, the pace would quicken.
“Things are going to be in full swing,” he said.
Robb praised the county’s efforts to get the job done.
He pointed out the project would have taken several years to complete and been more costly if the township had not used the county crew.
“We’re still ahead of the game,” Robb said.